Running a PIP while the hotel stays open
A property improvement plan, the renovation a hotel brand requires to keep a property on standard, rarely comes with permission to close. Rooms come out of inventory a few floors at a time, and every night a room is out of service is revenue the owner doesn’t get back. That turns furniture from a design question into a logistics one.
Plan around the floor schedule, not the factory
The contractor’s schedule says when each floor is stripped, finished and ready for furniture. Our production schedule copies it. Instead of one large delivery at the end, we build and ship in drops: for Hotel Marisol, four drops of roughly 80 rooms, each arriving within a 48-hour window of the floor being ready.
That means:
Production runs by floor, not by product. Each drop is a complete set of rooms, so a finished floor can go back on sale.
Everything is labeled by floor and room, so crews carry it straight to its place.
The first drop doubles as a final check. Anything we learn on floor one is fixed before floor two is packed.
Build a mock-up room early
On a PIP the mock-up room is where the brand, the owner and the designer agree. We build it at the plant, or ship it to site for a vacant room, before production starts. It’s the cheapest place to change a decision. Once 300 nightstands are finished, it’s the most expensive.
Protect the guests who are still staying
Installing next to occupied rooms changes how crews work. We schedule deliveries outside check-in and check-out peaks, use the service elevator only, unpack and remove packaging off the floor, and keep noise to agreed hours. The guest on the next floor shouldn’t know we’re there.
Store, don’t rush
Construction runs late. When a floor isn’t ready, finished goods wait at our plant at no charge for up to 90 days. That’s safer than storing furniture in a half-finished building, and it means a contractor delay doesn’t become damage.
What to send us at the start
The brand’s PIP scope and standards
The contractor’s floor-by-floor schedule
Room-type counts per floor
Access details: dock, elevator dimensions, hours
With those, we can return a drop schedule with the quote, and you’ll know before signing whether furniture fits the plan.
Written by
Maren Ashby
Co-founder & Managing Director
Journal
Keep reading

Counting back from opening night: when to order FF&E
Most FF&E delays are baked in before anything is built. Here’s how to count back from your opening date, week by week.
2 min

What a shop drawing should tell you, and what to check before you sign
A shop drawing is the contract for how a piece will be built. Here’s what ours include and the six things worth checking before you sign.
2 min

COM without the surprises: minimums, testing and lead time
Customer’s own material is the most common reason a custom seating order slips. How much to send, what we test and how to keep it on schedule.
2 min